Design and Implementation of The Buried Structure of Fire extinguishing tank and Red Crescent Engine Room

Design and Implementation of The Buried Structure of Fire extinguishing tank and Red Crescent Engine Room

Completed Projects
Category:
Design and Implementation
Location:
Tehran
Year:
2014
Project owner:
Red Crescent

Design and implementation of the buried structure of fire extinguishing tank and Red Crescent engine room
 

Excavation of fire extinguishing tank and engine room
Design and implementation of the buried structure of the 1.200.00 liter fire extinguishing tank
Design and implementation of engine room structure
Creating a concrete barrier to supply water from the main Red Crescent tank to the fire extinguishing tank
Start date: August 2014
End date: December 2014
Excavation area: 5400 cubic meters
Formatting area: 2000 square meters
Concreting area: 1100 cubic meters
Reinforcement size: 43 tons