Engine House and Hospital Treatment Plant
Engine House and Hospital Treatment Plant
Engine house and hospital treatment plant
Due to the limitation of space and the value of the land above Khatam, the motor house and treatment plant of Khatam were built in this area after the northern side of the cancer diagnosis and treatment center of Khatam was excavated.
Due to the existence of the water reservoir of Khatam on the north side of the excavation site, as well as the cancer diagnosis and treatment center of Khatam on the south side of the excavation site, the excavation operation has been highly sensitive and in order to strengthen the wall A self-drilling rod was used.
The treatment plant and motor house of Khatam will be built on a land of approximately 380 square meters and on 3 floors, and 2 floors are buried in the ground. Its skeleton is made of concrete with a concrete perimeter wall and a double-sided concrete slab roof.